City of Karratha

Project Dashboard

The City plans and allocates resources to regular, annual tasks to maintain our assets as well as capital works programs. 

Here you can view a detailed list of priorities for this financial year, including timelines and costs.

See monthly updates and how we are tracking.

Use the search function to find projects that are important to you, click ’read more’ to expand.

Total Projects

105

Total Budget

$40.0M

Completed Projects

49

Project Budget Start date Completion Status

Airport Terminal Building Improvements - Paving

Read more
175,000 2021/07/01 2021/11/30 Off Track

Airport Terminal Building Improvements - Fire detection

Read more
35,000 2021/07/01 2021/11/30 Off Track

Airport Terminal Building Improvements - Painting

Read more
10,000 2022/01/01 2022/02/28 Completed

Airport Terminal Building Improvements - Ceiling Panels

Read more
20,000 2021/07/01 2021/08/30 Completed

Airport Terminal Building Improvements - Chiller

Read more
350,000 2021/09/01 2022/05/30 Off Track

Airport Terminal Building Improvements - Air Cond. Upgrades

Read more
100,000 2021/08/01 2022/06/30 On Track

Airport Terminal Improvements - Baggage Handling

Read more
850,000 2021/07/01 2022/03/30 Off Track

Airport Terminal Carpark Improvements

Read more
350,000 2021/11/01 2022/05/30 On Track

Karratha Airport Entry Statement

Read more
591,111 2021/07/01 2021/10/30 Completed

Bulgarra Daycare Centre Improvements

Read more
25,000 2021/07/01 2021/09/30 Completed

Bulgarra Open Play Space Cyclone Repairs

Read more
150,000 2021/08/01 2021/12/30 Completed

Bus Shelter - Warambie Drive

Read more
60,000 2021/07/01 2022/04/30 Off Track

Bus Shelter - Welcome Road

Read more
95,120 2021/07/01 2022/04/30 On Track

City Housing - GBSC Yurra Partnership - Nine Houses, Nickol

Read more
3,355,796 2021/07/01 2022/06/30 On Track

City Housing - Two Houses, Nickol

Read more
1,300,000 2021/07/01 2022/06/30 Off Track

City Housing - Lot 7020 Development

Read more
250,000 2021/07/01 2022/06/30 On Track

Dampier Beach Enhancement

Read more
100,000 2021/10/01 2022/06/30 On Track

Dampier Boat Ramp Jetty Replacement

Read more
855,000 2021/07/01 2021/09/30 Completed

Dampier Drainage Upgrade

Read more
120,000 2021/10/01 2022/06/30 On Track

Dampier Pavilion Activation - Hampton Oval

Read more
100,000 2021/07/01 2022/03/30 Off Track

Dampier Pavilion Improvements - Hampton Oval

Read more
25,000 2021/08/01 2021/09/30 Completed

Designated Area Migration Agreement (DAMA)

Read more
60,000 2021/07/01 2022/06/30 On Track

Dewitt & Coolawanyah Road Intersection

Read more
70,000 2021/07/01 2022/06/30 On Track

Footpath Construction - Bayview Road, Stage 7

Read more
257,650 2022/03/01 2022/05/01 Completed

Footpath Construction - Bayview Road, Stage 6

Read more
566,512 2021/07/01 2021/10/01 Completed

Footpath Construction - Dampier Esplanade

Read more
70,000 2021/10/01 2021/11/30 Completed

Footpath Renewal - Rosemary Road to Baynton Drive

Read more
213,000 2021/10/01 2022/03/31 Off Track

Foreshore Management Plan - Gnoorea (40 Mile)

Read more
10,000 2022/02/01 2022/06/30 On Track

Gravel Road Re-sheeting - Cleaverville

Read more
297,380 2021/07/01 2021/09/30 Completed

Gravel Road Re-sheeting - Wittenoom Road, Roebourne

Read more
135,000 2021/08/01 2021/10/01 Completed

Gravel Road Re-sheeting - Woodbrook Road, Karratha Industrial Estate

Read more
100,000 2021/08/01 2021/10/01 Completed

Exercise Equipment - Hampton Oval

Read more
45,000 2021/09/01 2021/12/30 Off Track

City Housing - Hancock Way Subdivision

Read more
1,820,000 2021/07/01 2021/11/30 Completed

Karratha Golf Course Redevelopment

Read more
540,000 2021/07/01 2022/06/30 On Track

Karratha Leisureplex Building Improvements - Indoor Court Floors

Read more
90,000 2021/08/01 2021/11/30 Completed

Karratha Leisureplex Building Improvements - Water Line

Read more
100,000 2021/07/01 2021/12/30 Completed

Karratha Leisureplex Building Improvements - Squash Court

Read more
12,000 2021/08/01 2021/10/30 Completed

Karratha Leisureplex Building Improvements - Air Cond.

Read more
15,000 2021/07/01 2021/08/30 Completed

Karratha Leisureplex Improvement - Design Consultant

Read more
100,000 2021/07/01 2022/06/30 On Track

Karratha Leisureplex Improvement - Gym & Function Room Expansion

Read more
505,000 2021/07/01 2021/08/30 Completed

Karratha Leisureplex Improvement - Solar Initiative

Read more
4,125,000 2021/11/01 2022/06/30 On Track

Karratha Youth Shed Redevelopment

Read more
220,000 2021/07/01 2021/09/30 Completed

Kerb Renewal - Burrup Road, Roebourne

Read more
37,600 2021/10/01 2022/03/01 Completed

Kerb Renewal - Pringle Way, Wickham

Read more
41,360 2021/10/01 2022/03/31 Completed

Kerb Renewal - Walcott Drive, Wickham

Read more
202,100 2021/10/01 2022/03/01 Completed

Kevin Richards Memorial Oval Redevelopment - Change & Club Rooms

Read more
7,200,000 2021/10/01 2022/06/30 On Track

Kevin Richards Memorial Oval Redevelopment - Design Consultancy

Read more
100,000 2021/07/01 2022/06/30 On Track

Kevin Richards Memorial Oval Redevelopment - Northern Car Park

Read more
330,000 2021/10/01 2022/06/30 On Track

Kevin Richards Memorial Oval Redevelopment - Northern Play Space

Read more
325,000 2021/07/01 2021/10/30 Completed

Local Planning Scheme

Read more
60,000 2021/07/01 2022/04/30 Off Track

Madigan Road Design

Read more
200,000 2021/07/01 2022/05/31 On Track

Millars Well Daycare Centre Improvements

Read more
25,000 2021/08/01 2021/12/30 Completed

Mosquito Management Plan

Read more
10,000 2021/07/01 2021/09/30 On Track

Murujuga National Park Access Road

Read more
2,640,000 2021/07/01 2022/06/30 On Track

Old Roebourne Shire Office Improvements

Read more
50,000 2022/02/01 2022/04/30 Completed

Operations Centre Building Improvements

Read more
100,000 2021/07/01 2022/05/30 Off Track

Pam Buchanan Family Centre Building Improvements - Water

Read more
70,000 2021/09/01 2021/12/30 Off Track

Pam Buchanan Family Centre Building Improvements - Painting

Read more
47,000 2021/07/01 2021/08/30 Completed

Pam Buchanan Family Centre Building Improvements - Shade

Read more
140,000 2021/07/01 2021/09/30 Completed

Park Enhancement - Baynton West Park (Stage 2)

Read more
50,000 2022/03/01 2022/05/31 On Track

Park Enhancement - Dodd Court Park

Read more
150,000 2022/03/01 2022/05/31 Completed

Pilbara Hydrogen Cluster

Read more
75,000 2021/07/01 2022/03/30 Completed

Playground Upgrade - Cattrall Park, Pegs Creek

Read more
327,163 2022/01/01 2022/04/30 Off Track

Playground Upgrade - Church Way, Baynton

Read more
69,535 2022/01/01 2022/04/01 On Track

Playground Upgrade - Delambre Park, Nickol

Read more
69,535 2022/01/01 2022/04/01 On Track

Playground Upgrade - Miles Loop, Baynton

Read more
69,535 2022/01/01 2022/04/01 On Track

Playground Upgrade - Tambrey Park, Nickol

Read more
69,535 2022/01/01 2022/04/01 On Track

Point Samson Fishing Jetty

Read more
45,000 2021/12/01 2021/08/30 Completed

Point Samson Foreshore Restoration

Read more
265,000 2021/08/01 2021/11/30 Completed

Public Health Plan

Read more
40,520 2021/07/01 2021/10/30 Off Track

REAP Building Improvements

Read more
20,000 2021/07/01 2021/11/30 Completed

Reticulation Upgrade - Bayview Road, Karratha

Read more
50,000 2021/12/01 2022/06/01 Completed

Reticulation Upgrade - City of Karratha Administration Building

Read more
50,000 2022/01/01 2022/06/01 Off Track

Reticulation Upgrade - Pam Buchanan Family Centre

Read more
50,000 2021/09/01 2021/12/31 Off Track

Reticulation Upgrade - Tambrey Park, Nickol

Read more
200,000 2021/09/01 2021/12/31 Completed

Road Construction - Coolawanyah Road

Read more
2,438,577 2021/07/01 2022/06/30 On Track

Road Reseal - Burrup Road, Roebourne

Read more
33,048 2022/03/01 2022/05/31 Completed

Road Reseal - Kudjuna Way, Roebourne

Read more
4,141 2022/03/01 2022/05/01 Completed

Road Reseal - Pringle Way, Wickham

Read more
82,500 2022/03/01 2022/05/01 Completed

Road Reseal - Walcott Drive, Wickham

Read more
247,500 2022/03/01 2022/05/31 Completed

Roebourne Basketball Courts Resurfacing

Read more
150,000 2021/12/01 2022/06/30 On Track

Roebourne Dalgety House Improvements

Read more
35,000 2022/03/01 2022/05/30 Completed

Roebourne Streetscape Master Plan

Read more
100,000 2021/07/01 2022/04/30 On Track

Roundabout Enhancements - Nickol West

Read more
112,500 2022/02/01 2022/06/30 On Track

Roundabout Enhancements - Wickham

Read more
112,500 2022/02/01 2022/06/01 On Track

Shakespeare Precinct Scheme Amendment

Read more
30,000 2021/07/01 2022/06/30 Off-track

Staff Housing Building Improvements

Read more
250,000 2021/09/01 2022/06/30 Completed

Dampier Storm Water Structure Upgrade

Read more
254,000 2021/07/01 2021/11/30 Completed

Strategic Land Acquisition

Read more
2,605,000 2021/07/01 2021/12/30 On Track

Streetscape and Verges Program

Read more
200,000 2022/02/01 2022/06/30 On Track

Streetscape Enhancement, Bayview Road

Read more
265,000 2021/08/01 2021/11/01 Completed

Streetscape Enhancement, Dampier Road

Read more
265,000 2021/08/01 2021/11/30 Completed

The Quarter - Tenancy Creation

Read more
200,000 2021/07/01 2021/12/30 Completed

Water Tank Lighting

Read more
120,000 2021/07/01 2021/12/30 Off Track

Website Development for City of Karratha

Read more
120,000 2021/07/01 2021/10/30 On Track

Weed Management Strategy

Read more
20,000 2021/08/01 2022/05/31 On Track

Wickham Community Hub - Public Art

Read more
85,000 2021/07/01 2022/01/30 Off Track

Wickham Recreation Precinct Improvements Study

Read more
200,000 2022/01/01 2022/06/30 On Track

Windy Ridge Sporting Precinct Feasibility

Read more
100,000 2022/01/01 2022/06/30 On Track

Road Reseal - DeWitt Road, Stove Hill

Read more
41,600 2022/01/01 2022/05/30 On Track

Road Reseal - Harding Street, Roebourne

Read more
102,960 2022/01/01 2022/05/30 Completed

Road Reseals - Rowell Street, Gap Ridge

Read more
23,175 2022/01/01 2022/05/30 Completed

Road Reseal - Murray Street, Point Samson

Read more
32,560 2022/01/01 2022/05/30 Completed

Road Reseal - Collect Close, Millars Well

Read more
20,020 2022/01/01 2022/05/30 Completed

Shakespeare Street, Bulgarra Service Worker Unit Accommodation Redevelopment

Read more
322,000 2021/12/01 2022/06/30 On Track